Concrete Repair Works (Additional Structures) in Shoaibah Power & Desalination Plant (Phase-1)
The purpose of this project is to carry out the concrete repair works of the additional structures. Total area to be demolished & re-constructed & repaired :112,823 m2 Total Concrete Amount: 15,777 m3 Total Steel Reinforced : 2,430 Ton Total Structural Steel : 489 Ton Total Excavation & Back-fill Amount: 26,294 m3
- Client
- Saline Water Conversion Corporation (SWCC)
- Location
- Shoaibah
- Timeline
- 2010 — 2014
- Specifications
- Refurbishment